Monitoring Report Update Meeting for NEWS Project.

E-mail Print PDF

tongan-zeal

22nd November, 2019 The CEO for MEIDECC Mr Paula P. Ma’u met with key stakeholders this morning at MEIDECC’s conference room to discuss and report on the progress of the Nationwide Early Warning System and Strengthening Disaster Communications (NEWS Project).

 


Construction site of the new TBC Building Station, Fasi mo e Afi.


The meeting was attended by representatives from Japan International Cooperation Agency (JICA), Ministry of Finance, Tonga Broadcasting Commission (TBC), contractors from Japan and the Director of the Department of Communications.

Fifty per cent of the work scheduled at the construction of the new TBC Studio Building has been completed and the construction is expected to be completed and handover at the end of the April next year, 2020. The installation of equipment such as siren masts and Radio Activated Receiver is set to commence next year, and all will be completed and handover at the end of August next year 2020.

CEO Paula P. Ma’u thanked JICA, the Consultant Engineer Yachio Engineering Co. Ltd and the contractors from Japan, including the local contractor ‘Ofa Construction for all the hard work to bring the project to 50% completion and look forward to successful handover next year.

New Transmitter Hut, Popua.

ENDS

Issued by the: Ministry of Meteorology, Energy, Information, Disaster Management, Environment, Climate Change and Communications.

Last Updated ( Tuesday, 07 July 2020 16:37 )  

Who's Online

We have 552 guests online

CONSULATES/EMBASSIES

PUBLIC ENTERPRISES